Major Milestones Reached as Steel, Roofing and Exterior Work Progress on 2024 Facilities Referendum Sites

Major Milestones Reached as Steel, Roofing and Exterior Work Progress on 2024 Facilities Referendum Sites

Sherman Middle School and Shabazz High School

What’s New?

Structural steel erection was completed this past week! Ironworkers will remain onsite to complete metal decking and miscellaneous detailing in preparation for future slab-on-deck pours. Concrete work continues throughout the building, with both slabs-on-grade and slabs-on-deck progressing. Most recently, the stage and mechanical room slabs, along with several mechanical equipment pads, were poured. Underground electrical and plumbing work continues ahead of upcoming concrete pours.

Interior CMU block installation continues to progress south through the building, while cast stone installation is beginning along the north face.

Building envelope work also continues to make steady progress. Exterior stud framing and sheathing are advancing along the west and south elevations of the Shabazz High School. Weather barrier installation, including associated detailing and spray-applied work, follows the sheathing installation. Exterior insulated sheathing, roof blocking, and window blocking are also progressing, followed by a final round of weather barrier detailing to complete the exterior wall assemblies prior to brick and metal panel work

The Past Week

  • Geothermal lateral piping and connections to Darcy wells.
  • Interior CMU Wall work in the Shabazz High School.
  • Exterior sheathing and weather barrier on the West side

Coming Up in Weeks Ahead

  • EPDM roofing will begin next week.
  • Spray applied fireproofing work will begin in 2 weeks.
  • Slab-on-grade and slab-on-deck work will be completed by the end of October.

Did You Know: This project will use over 1,250,000 pounds of structural steel, equivalent to the weight of roughly 104 African elephants!

Black Hawk Middle School & Gompers Elementary School

What’s New

Over the past two weeks, all concrete slab-on-metal-deck pours were completed, and the final major area of structural steel was erected. The building's structure is now nearly complete, with four slab-on-grade pours completed during this period.

Exterior framing is underway along the west side of the building, while interior framing has been completed in all elementary school classrooms.

The first section of roofing was completed over the elementary school classrooms, and work will continue progressing north. Crews are preparing to install the first window frames in the building, and masons will return to the site to begin constructing the first interior concrete block walls.

What’s Coming Next

  • Continue interior framing for the elementary school offices
  • Start window framing around the elementary classroom wings
  • Beginning interior concrete block walls in the lower level
  • Slab pours for the remainder of the building

Did You Know?

The interior and exterior framing is made from cold-formed steel studs. “Cold-formed" refers to the manufacturing process as the studs are formed at room temperature instead of high heat. Cold-formed steel is strong and can be formed into a variety of shapes, making it an ideal building material.